Construction In Progress
Civil Engineering Corporation of Hakik 4 Redevelopment
페이지 정보
작성자 BAN SEUK CONSTRUCTION CO., LTD 작성일2022-08-11본문
- Project title: Civil Engineering Corporation of Hakik 4 Redevelopment
- Construction Period: August 5, 2022 to May 30, 2025
- Main Contractor: HANWHA ENGINEERING & CONSTRUCTION CORP.
- Client: Hakik District 4 Housing Redevelopment and Maintenance Project Association
- Overview of Construction: Earthworks and temporary facility construction work, CIP, grouting, auxiliary civil works, etc.
Construction Information
[Work scope]
1) Earthwork : Excavation 136,000㎥, Refilling 4,500㎥, Disposal 136,000㎥
2) Temporary facility construction woek : CIP 16,000m / ASG grouting 11,986m / Post-Pile 1,200m / Wale 2,680m / E/A 6,634m / Raker Pile
3) Auxiliary civil works. etc.